Duct work and metal studs

Now that the roof is water tight the contractor has concentrated on the inside of the club house. All outside walls have been framed, insulated, and dry-walled. The interior walls have been framed with metal studs. The duct work for heating, air conditioning, and cooking ventilation is on going. It is also a busy time for the plumber and electrician running the services required throughout the walls. The basement floor was poured last Thursday and framing immediately started on framing walls in the basement on Friday. Enjoy the pictures.  Until next time…
David

Another view showing interior walls

Snack bar counter framed

View of the Basement